Smart Energy Network (SEN)
Project goals
The project goal is to find new, accurate, fast and easy-to-use tools for control and protection of an active distribution system by using more real-time information and thus contribute to its reliability - shortening the time of fault location, isolation and power restoration. All these with the help of secure information and communication technology (ICT), as well as through the implementation of advanced protection and control algorithms. In co-operation and with the help of application guarantors, we want to transfer the project results to the environment of the real distribution network and increase their usability and commercial potential through experimental development.
Keywords
distribution networksubstationcentralized protection systemsampled values (SV)process buscurrent sensorsvoltage sensorsadaptive protectioncybersecuritycommunication technology for smart grids
Public support
Provider
Technology Agency of the Czech Republic
Programme
Programme for funding of applied research, experimental development, and innovation THETA
Call for proposals
THETA 1 (STA02018TK010)
Main participants
Vysoké učení technické v Brně / Fakulta elektrotechniky a komunikačních technologií
Contest type
VS - Public tender
Contract ID
TK01030094 - Smlouva o poskytnutí podpory
Alternative language
Project name in Czech
Inteligentní energetické sítě
Annotation in Czech
Cílem projektu je najít nové přesné, rychlé a snadno použitelné nástroje pro řízení a chránění aktivní distribuční soustavy s využitím více informací v reálném čase a přispět tak ke zvýšení její spolehlivosti a zkrácení doby regenerace po poruše. To vše za pomoci bezpečné informační a komunikační technologie (ICT), jakož i prostřednictvím implementace vhodných algoritmů chránění a řízení. V kooperaci a s přispěním aplikačních garantů chceme přenést výsledky projektu do prostředí reálné distribuční sítě a prostřednictvím experimentálního vývoje zvýšit jejich využitelnost a komerční potenciál.
Scientific branches
R&D category
VV - Exeperimental development
OECD FORD - main branch
20704 - Energy and fuels
OECD FORD - secondary branch
20201 - Electrical and electronic engineering
OECD FORD - another secondary branch
20201 - Electrical and electronic engineering
JA - Electronics and optoelectronics
JB - Sensors, detecting elements, measurement and regulation
JE - Non-nuclear power engineering, energy consumption and utilization
JT - Propulsion, engines and fuels
Completed project evaluation
Provider evaluation
U - Uspěl podle zadání (s publikovanými či patentovanými výsledky atd.)
Project results evaluation
The investigation team, including the application guarantors, can be assessed as professional, without any doubts. Expert reports and statements of opponents and application guarantors clearly appreciate the professional side of the project solution. The project demonstrably achieved the set goals and planned results. The results have application potential. The project succeeded according to the assignment. For assessment A, a sufficient number of secondary outputs in the form of professional articles published, for example, in foreign peer-reviewed journals is not submitted.
Solution timeline
Realization period - beginning
Sep 1, 2018
Realization period - end
Aug 31, 2023
Project status
U - Finished project
Latest support payment
Feb 28, 2023
Data delivery to CEP
Confidentiality
C - Předmět řešení projektu podléhá obchodnímu tajemství (§ 504 Občanského zákoníku), ale název projektu, cíle projektu a u ukončeného nebo zastaveného projektu zhodnocení výsledku řešení projektu (údaje P03, P04, P15, P19, P29, PN8) dodané do CEP, jsou upraveny tak, aby byly zveřejnitelné.
Data delivery code
CEP24-TA0-TK-U
Data delivery date
Jun 28, 2024
Finance
Total approved costs
35,567 thou. CZK
Public financial support
30,460 thou. CZK
Other public sources
5,335 thou. CZK
Non public and foreign sources
0 thou. CZK
Basic information
Recognised costs
35 567 CZK thou.
Public support
30 460 CZK thou.
85%
Provider
Technology Agency of the Czech Republic
OECD FORD
Energy and fuels
Solution period
01. 09. 2018 - 31. 08. 2023