Research on the ecologic binder based on the geopolymer structure which is able to immobilize the potentially harmful substances from bulk-cargo produced industrial wastes, and its further application into building industry
Project goals
The aim of this project is to develop the alkali activated aluminosilicate composite from unused or waste materials which will be able to fix the most possible amounts of toxic substances in its structure and at the same time will be applicable in building industry.
Keywords
alkali-activated aluminosilicategeopolymerizationimmobilizationpotentialy harmfull substances
Public support
Provider
Ministry of Education, Youth and Sports
Programme
Health and quality of life
Call for proposals
Zdravý a kvalitní život 2 (SMSM20082B2)
Main participants
—
Contest type
VS - Public tender
Contract ID
1182/2010-31
Alternative language
Project name in Czech
Výzkum a vývoj ekologického pojiva na bázi geopolymerních struktur se schopností imobilizace potenciálně nebezpečných látek z velkoobjemově produkovaných průmyslových odpadů a jeho následné aplikace ve stavebnictví
Annotation in Czech
Cílem projektu je vyvinout alkalicky aktivovaný aluminosilikát ze v současnosti nevyužívaných odpadních surovin, jěž bude schopen ve své strutuře zadržovat co možná největší množství polutantů a současně bude použitelný ve stavebnictví.
Scientific branches
R&D category
ZV - Basic research
CEP classification - main branch
DM - Solid waste and its control, recycling
CEP - secondary branch
JI - Composite materials
CEP - another secondary branch
JP - Industrial processes and processing
10511 - Environmental sciences (social aspects to be 5.7)
20501 - Materials engineering
20505 - Composites (including laminates, reinforced plastics, cermets, combined natural and synthetic fibre fabrics; filled composites)
20705 - Remote sensing
20706 - Marine engineering, sea vessels
20707 - Ocean engineering
Completed project evaluation
Provider evaluation
U - Uspěl podle zadání (s publikovanými či patentovanými výsledky atd.)
Project results evaluation
The course of researching as well plan results fully agree with the plan task.The research plan provides a quality,in practice well exploitable and current recommandation.Submitted final solution is the example of successful cooperation of universities with the practice.
Solution timeline
Realization period - beginning
Mar 1, 2008
Realization period - end
Oct 31, 2011
Project status
U - Finished project
Latest support payment
Feb 25, 2011
Data delivery to CEP
Confidentiality
S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů
Data delivery code
CEP12-MSM-2B-U/01:1
Data delivery date
Jul 3, 2012
Finance
Total approved costs
9,000 thou. CZK
Public financial support
8,084 thou. CZK
Other public sources
0 thou. CZK
Non public and foreign sources
916 thou. CZK
Basic information
Recognised costs
9 000 CZK thou.
Public support
8 084 CZK thou.
89%
Provider
Ministry of Education, Youth and Sports
CEP
DM - Solid waste and its control, recycling
Solution period
01. 03. 2008 - 31. 10. 2011