Probabilistic reliability and risk assessment of structures
Project goals
The project will promote international activities of the Klokner Institute CTU in Prague, concerning development of the methodology for reliability analysis and risk assessment of structures in persistent and accidental design situations. The project team will participate in the international research within JCSS (Joint Committee for Structural Safety), particularly concerning the development of the Probabilistic Model Code. Advanced methods for structural verification including probabilistic methods and global resistance factor method for non-linear analyses will be improved.
Keywords
reliability of structuresrisk assessmentactionsprobabilistic optimisation
Public support
Provider
Ministry of Education, Youth and Sports
Programme
INGO II
Call for proposals
INGO II 1 (SMSM2011LG1)
Main participants
—
Contest type
VS - Public tender
Contract ID
12321/2011-321
Alternative language
Project name in Czech
Pravděpodobnostní metody hodnocení spolehlivosti a rizik konstrukcí
Annotation in Czech
Cílem projektu je zajištění spolupráce Kloknerova ústavu s výzkumnou organizací JCSS (Joint Committee on Structural Safety) na mezinárodním výzkumu zaměřeném na rozvoj metodik analýz a hodnocení rizik konstrukcí ovlivněných extrémními zatíženími a nepříznivými účinky prostředí. V rámci řešení projektu se budou rozvíjet metody pro ověřování spolehlivosti konstrukcí: metoda globálních součinitelů odolnosti a přímé pravděpodobnostní metody. Dílčím cílem projektu je specifikace dosud chybějících pravděpodobnostních modelů základních veličin do modelové příručky JCSS.
Scientific branches
Completed project evaluation
Provider evaluation
V - Vynikající výsledky projektu (s mezinárodním významem atd.)
Project results evaluation
Project was focused on the assurance of international activities aimed at development of methodological approaches for the reliability and risk assessment of structures under effects of extreme actions and adverse environment. Project outcomes include contributions for international conferences, scientific journals and working materials for international research organisations.
Solution timeline
Realization period - beginning
Mar 1, 2011
Realization period - end
Dec 31, 2013
Project status
U - Finished project
Latest support payment
Feb 20, 2013
Data delivery to CEP
Confidentiality
S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů
Data delivery code
CEP14-MSM-LG-U/01:1
Data delivery date
Jun 30, 2014
Finance
Total approved costs
1,275 thou. CZK
Public financial support
1,146 thou. CZK
Other public sources
0 thou. CZK
Non public and foreign sources
129 thou. CZK
Recognised costs
1 275 CZK thou.
Public support
1 146 CZK thou.
0%
Provider
Ministry of Education, Youth and Sports
CEP
JN - Civil engineering
Solution period
01. 03. 2011 - 31. 12. 2013