ELI - EXTREME LIGHT INFRASTRUCTURE - phase 2

Public support

  • Provider

    Ministry of Education, Youth and Sports

  • Programme

  • Call for proposals

  • Main participants

    Extreme Light Infrastructure ERIC (ELI ERIC)

  • Contest type

    OP - EU Operational Programme

  • Contract ID

    CZ.02.1.01/0.0/0.0/15_008/0000162

Alternative language

  • Project name in Czech

    ELI - EXTREME LIGHT INFRASTRUCTURE - fáze 2

  • Annotation in Czech

    Hlavními cíli projektu ELI je vybudování nejmodernějšího laserového zařízení a realizace řady výzkumných a aplikačních projektů zahrnujících interakci světla s hmotou na intenzitě, která je asi 100 krát větší než současné dosažitelné hodnoty. ELI bude dodávat ultrakrátké laserové pulsy trvající typicky několik femtosekund (10-15 fs) a bude produkovat výkon až 200 PW

Scientific branches

  • R&D category

    IF - RDI infrastructure

  • CEP classification - main branch

    BH - Optics, masers and lasers

  • CEP - secondary branch

    BF - Elementary particle theory and high energy physics

  • CEP - another secondary branch

  • OECD FORD - equivalent branches <br>(according to the <a href="http://www.vyzkum.cz/storage/att/E6EF7938F0E854BAE520AC119FB22E8D/Prevodnik_oboru_Frascati.pdf">converter</a>)

    10303 - Particles and field physics<br>10306 - Optics (including laser optics and quantum optics)

Completed project evaluation

  • Provider evaluation

    V - Vynikající výsledky projektu (s mezinárodním významem atd.)

  • Project results evaluation

    Project ELI Phase 2 was in realization from 1. 1. 2016 till 31. 12. 2018 with total budget over 1,8 billions CZK. Project was follow up of the project ELI Phase 1. The main goals of both phases were to build, equip and to put into operation the new laser facility in Dolni Brezany. All the main goals were fullfiled. In the current time the building is finished and completely operating. All the technologies were delivered and tested from the parameter point of view. The user operation is starting on the laser and experimental stations.

Solution timeline

  • Realization period - beginning

    Jan 1, 2016

  • Realization period - end

    Dec 31, 2018

  • Project status

    U - Finished project

  • Latest support payment

    Feb 1, 2017

Data delivery to CEP

  • Confidentiality

    S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů

  • Data delivery code

    CEP19-MSM-EF-U

  • Data delivery date

    Mar 21, 2023

Finance

  • Total approved costs

    1,859,488 thou. CZK

  • Public financial support

    185,949 thou. CZK

  • Other public sources

    92,974 thou. CZK

  • Non public and foreign sources

    0 thou. CZK