Optimisation study of wastewater release monitoring from nuclear power plant

Project goals

It is necessary to check up the kinetics of transport of contaminated water from NPP into the watercourse and then in watercourse in case of normal monitoring and in case of radiological emergency. The main goal is to make the prediction for transport ofcontaminants in particular profiles downstream from the releases of wastewater from NPP, finally for the boundary profiles.

Keywords

kinetics of transportcontaminated water

Public support

  • Provider

    State Office for Nuclear Safety

  • Programme

  • Call for proposals

  • Main participants

  • Contest type

    VZ - Public procurement

  • Contract ID

    49141/KÚ/2006/ikoh

Alternative language

  • Project name in Czech

    Optimalizace monitoringu kapalných výpustí z jaderných elektráren

  • Annotation in Czech

    Výsledky monitoringu obsahu ra-látek v povrchových vodách jsou ovlivňovány vypouštěním ?radioaktivních? odpadních vod do proudu ostatních vod vypouštěných JE, zejména odluhů chladících věží a z čističek odpadních vod. Výsledky tohoto monitoringu neumožňují posoudit kinetiku dotoku kontaminantů v odpadních vodách z JE. Cílem je ověřit doby dotoku radionuklidy kontaminovaných vod pro prognózu transportu kontaminantů v jednotlivých profilech níže po toku pod zaústěním odpadních vod; v konečné fázi až po uzávěrové (hraniční) profily.

Scientific branches

  • R&D category

    NV - Nonindustrial research (Applied research excluded Industrial research)

  • CEP classification - main branch

    JF - Nuclear energy

  • CEP - secondary branch

  • CEP - another secondary branch

  • 20305 - Nuclear related engineering; (nuclear physics to be 1.3);

Completed project evaluation

  • Provider evaluation

    U - Uspěl podle zadání (s publikovanými či patentovanými výsledky atd.)

  • Project results evaluation

    Result fully convenient needs SONS.

Solution timeline

  • Realization period - beginning

    Sep 21, 2006

  • Realization period - end

    Dec 31, 2007

  • Project status

    U - Finished project

  • Latest support payment

    Feb 16, 2007

Data delivery to CEP

  • Confidentiality

    S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů

  • Data delivery code

    CEP08-SUJ-JC-U/02:2

  • Data delivery date

    May 13, 2008

Finance

  • Total approved costs

    740 thou. CZK

  • Public financial support

    740 thou. CZK

  • Other public sources

    0 thou. CZK

  • Non public and foreign sources

    0 thou. CZK

Basic information

Recognised costs

740 CZK thou.

Public support

740 CZK thou.

100%


Provider

State Office for Nuclear Safety

CEP

JF - Nuclear energy

Solution period

21. 09. 2006 - 31. 12. 2007