Optimization of a tunnel lining with respect to integrated life cycle assessment
Identifikátory výsledku
Kód výsledku v IS VaVaI
<a href="https://www.isvavai.cz/riv?ss=detail&h=RIV%2F00216305%3A26110%2F16%3APU118506" target="_blank" >RIV/00216305:26110/16:PU118506 - isvavai.cz</a>
Výsledek na webu
—
DOI - Digital Object Identifier
—
Alternativní jazyky
Jazyk výsledku
angličtina
Název v původním jazyce
Optimization of a tunnel lining with respect to integrated life cycle assessment
Popis výsledku v původním jazyce
This contribution describes the design of cross-section dimension (tunnel lining thickness) and reinforcement design optimization of a concrete structure using the DBSA (Deterministic Based Structure Optimization) approach. The target function is defined as a multicriterial problem and will include economic and ecological aspects associated not only with the production of concrete members but also with their maintenance during utilization. From the mathematical viewpoint, the range of allowable solutions are defined by constraining conditions expressed by relations derived from equations of equilibrium (the solution of optimization calculations for a structure with a Winkler foundation using the finite element method) and the reliability conditions that apply to a reinforced concrete structure.
Název v anglickém jazyce
Optimization of a tunnel lining with respect to integrated life cycle assessment
Popis výsledku anglicky
This contribution describes the design of cross-section dimension (tunnel lining thickness) and reinforcement design optimization of a concrete structure using the DBSA (Deterministic Based Structure Optimization) approach. The target function is defined as a multicriterial problem and will include economic and ecological aspects associated not only with the production of concrete members but also with their maintenance during utilization. From the mathematical viewpoint, the range of allowable solutions are defined by constraining conditions expressed by relations derived from equations of equilibrium (the solution of optimization calculations for a structure with a Winkler foundation using the finite element method) and the reliability conditions that apply to a reinforced concrete structure.
Klasifikace
Druh
D - Stať ve sborníku
CEP obor
—
OECD FORD obor
20101 - Civil engineering
Návaznosti výsledku
Projekt
Výsledek vznikl pri realizaci vícero projektů. Více informací v záložce Projekty.
Návaznosti
P - Projekt vyzkumu a vyvoje financovany z verejnych zdroju (s odkazem do CEP)
Ostatní
Rok uplatnění
2016
Kód důvěrnosti údajů
S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů
Údaje specifické pro druh výsledku
Název statě ve sborníku
CESB16 - Central Europe toward Sustainable Building 2016
ISBN
978-80-271-0248-8
ISSN
—
e-ISSN
—
Počet stran výsledku
8
Strana od-do
911-918
Název nakladatele
Grada
Místo vydání
Praha
Místo konání akce
Praha
Datum konání akce
22. 6. 2016
Typ akce podle státní příslušnosti
WRD - Celosvětová akce
Kód UT WoS článku
—