Study of transient events in pumping station before reconstruction
Identifikátory výsledku
Kód výsledku v IS VaVaI
<a href="https://www.isvavai.cz/riv?ss=detail&h=RIV%2F00216305%3A26210%2F23%3APU156221" target="_blank" >RIV/00216305:26210/23:PU156221 - isvavai.cz</a>
Výsledek na webu
—
DOI - Digital Object Identifier
—
Alternativní jazyky
Jazyk výsledku
angličtina
Název v původním jazyce
Study of transient events in pumping station before reconstruction
Popis výsledku v původním jazyce
The pumping station supplies water from the river to the reservoir, from where the water is further pumped into the technological operations of the power plant. The reservoir is placed 150 m above the river. When the pumps start or stop, the cone valve located on the discharge side open or close slowly. The pressure vessels with water and air protect the system against the hydraulic shock (water hammer). The article describes a numerical analysis of the possible replacement of cone valve with non-slam check valves (nozzle check valves), which are cheaper and have easier maintenance and better shock protection (water hammer protection system). There is a special attention paid to the pressure shocks during the transients. As the non-slam check valves do not allow controlled closing, any operational shutdown of the pumps is identical to a failure, and it can place higher demand on the entire system.
Název v anglickém jazyce
Study of transient events in pumping station before reconstruction
Popis výsledku anglicky
The pumping station supplies water from the river to the reservoir, from where the water is further pumped into the technological operations of the power plant. The reservoir is placed 150 m above the river. When the pumps start or stop, the cone valve located on the discharge side open or close slowly. The pressure vessels with water and air protect the system against the hydraulic shock (water hammer). The article describes a numerical analysis of the possible replacement of cone valve with non-slam check valves (nozzle check valves), which are cheaper and have easier maintenance and better shock protection (water hammer protection system). There is a special attention paid to the pressure shocks during the transients. As the non-slam check valves do not allow controlled closing, any operational shutdown of the pumps is identical to a failure, and it can place higher demand on the entire system.
Klasifikace
Druh
D - Stať ve sborníku
CEP obor
—
OECD FORD obor
20301 - Mechanical engineering
Návaznosti výsledku
Projekt
<a href="/cs/project/TK70020001" target="_blank" >TK70020001: Digitalizace infrastruktury dodávky pitné vody pro optimalizaci vztahu voda-energie</a><br>
Návaznosti
P - Projekt vyzkumu a vyvoje financovany z verejnych zdroju (s odkazem do CEP)
Ostatní
Rok uplatnění
2023
Kód důvěrnosti údajů
S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů
Údaje specifické pro druh výsledku
Název statě ve sborníku
Pressure Surges 2023
ISBN
9789038657103
ISSN
—
e-ISSN
—
Počet stran výsledku
11
Strana od-do
35-45
Název nakladatele
TU/e
Místo vydání
Groene Loper 3, 5612 AE Eindhoven The Netherland
Místo konání akce
Eindhoven
Datum konání akce
12. 4. 2023
Typ akce podle státní příslušnosti
WRD - Celosvětová akce