Steam and feedwater piping assessment outside the containment at Metsamor NPP
Identifikátory výsledku
Kód výsledku v IS VaVaI
<a href="https://www.isvavai.cz/riv?ss=detail&h=RIV%2F46356088%3A_____%2F12%3A%230001433" target="_blank" >RIV/46356088:_____/12:#0001433 - isvavai.cz</a>
Výsledek na webu
—
DOI - Digital Object Identifier
—
Alternativní jazyky
Jazyk výsledku
angličtina
Název v původním jazyce
Steam and feedwater piping assessment outside the containment at Metsamor NPP
Popis výsledku v původním jazyce
In this paper, experience and results of the Pipe integrity design project applied to Unit 2 of Armenian NPP in Metsamor are presented. The feedwater and steam piping lines, which were covered by the Project, are located in the turbine hall on the elevation of +14.7 m, outside the containment. Piping was assessed from point of view of both pipe rupture postulation criteria defined in SRP 3..6.2 [2] and in BTP 3.4 [4] and seismic margin requirements [5] based on the international practice for the NPPs inoperation. Concerning hydrodynamic calculations, possible causes of steam and water hammer were assessed. To lower the stresses in critical locations and to solve the effects of steam/feedwater/emergency feedwater pipe whip, some measures have been proposed installations of whip restraints, hydraulic snubbers, etc. Detailed design files have been prepared for the proposed measures. Within this project, ISI program was conducted, with application to the most loaded locations. Proposal of
Název v anglickém jazyce
Steam and feedwater piping assessment outside the containment at Metsamor NPP
Popis výsledku anglicky
In this paper, experience and results of the Pipe integrity design project applied to Unit 2 of Armenian NPP in Metsamor are presented. The feedwater and steam piping lines, which were covered by the Project, are located in the turbine hall on the elevation of +14.7 m, outside the containment. Piping was assessed from point of view of both pipe rupture postulation criteria defined in SRP 3..6.2 [2] and in BTP 3.4 [4] and seismic margin requirements [5] based on the international practice for the NPPs inoperation. Concerning hydrodynamic calculations, possible causes of steam and water hammer were assessed. To lower the stresses in critical locations and to solve the effects of steam/feedwater/emergency feedwater pipe whip, some measures have been proposed installations of whip restraints, hydraulic snubbers, etc. Detailed design files have been prepared for the proposed measures. Within this project, ISI program was conducted, with application to the most loaded locations. Proposal of
Klasifikace
Druh
D - Stať ve sborníku
CEP obor
JF - Jaderná energetika
OECD FORD obor
—
Návaznosti výsledku
Projekt
—
Návaznosti
N - Vyzkumna aktivita podporovana z neverejnych zdroju
Ostatní
Rok uplatnění
2012
Kód důvěrnosti údajů
S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů
Údaje specifické pro druh výsledku
Název statě ve sborníku
PROCEEDINGS OF THE ASME PRESSURE VESSELS AND PIPING CONFERENCE, VOL 3: DESIGN AND ANALYSIS
ISBN
978-0-7918-4453-3
ISSN
—
e-ISSN
—
Počet stran výsledku
6
Strana od-do
187-192
Název nakladatele
ASME
Místo vydání
—
Místo konání akce
Baltimore, USA
Datum konání akce
1. 1. 2011
Typ akce podle státní příslušnosti
WRD - Celosvětová akce
Kód UT WoS článku
000320340600026