Comparison of Deterministic Approach and Monte Carlo Methods for Stochastic PERT Chart
Identifikátory výsledku
Kód výsledku v IS VaVaI
<a href="https://www.isvavai.cz/riv?ss=detail&h=RIV%2F00216305%3A26510%2F14%3APU109911" target="_blank" >RIV/00216305:26510/14:PU109911 - isvavai.cz</a>
Výsledek na webu
—
DOI - Digital Object Identifier
—
Alternativní jazyky
Jazyk výsledku
angličtina
Název v původním jazyce
Comparison of Deterministic Approach and Monte Carlo Methods for Stochastic PERT Chart
Popis výsledku v původním jazyce
The paper deals with a comparison of two different approaches (deterministic approach and Monte Carlo method) calculation of the probability of completion of the project. The base assumption of authors can be expressed: The difference between the resultsobtained by the Monte Carlo method and deterministic approach is not significant with increasing number of simulations (iterations). For this reason the hypothesis was formulated: There is no statistically significant difference between the calculated probabilities, i.e. both approaches are identical from application point of view. The problem was solved using the example project whose model (network chart) contained 18 nodes and 24 activities (18 real. 6 fictions). For each activity have been known three time estimates (pessimistic, most likely, optimistic). The planned date of completion of the project was selected at 200 time units and it was calculated the probability of completion of the project by deterministic approach and Monte
Název v anglickém jazyce
Comparison of Deterministic Approach and Monte Carlo Methods for Stochastic PERT Chart
Popis výsledku anglicky
The paper deals with a comparison of two different approaches (deterministic approach and Monte Carlo method) calculation of the probability of completion of the project. The base assumption of authors can be expressed: The difference between the resultsobtained by the Monte Carlo method and deterministic approach is not significant with increasing number of simulations (iterations). For this reason the hypothesis was formulated: There is no statistically significant difference between the calculated probabilities, i.e. both approaches are identical from application point of view. The problem was solved using the example project whose model (network chart) contained 18 nodes and 24 activities (18 real. 6 fictions). For each activity have been known three time estimates (pessimistic, most likely, optimistic). The planned date of completion of the project was selected at 200 time units and it was calculated the probability of completion of the project by deterministic approach and Monte
Klasifikace
Druh
D - Stať ve sborníku
CEP obor
AE - Řízení, správa a administrativa
OECD FORD obor
—
Návaznosti výsledku
Projekt
—
Návaznosti
S - Specificky vyzkum na vysokych skolach
Ostatní
Rok uplatnění
2014
Kód důvěrnosti údajů
S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů
Údaje specifické pro druh výsledku
Název statě ve sborníku
Vision 2020: Sustainable Growth, Economic Development, and Global Competitiveness
ISBN
978-0-9860419-2-1
ISSN
—
e-ISSN
—
Počet stran výsledku
7
Strana od-do
1923-1929
Název nakladatele
International Business Information Management Association (IBIMA)
Místo vydání
Valencia, Spain
Místo konání akce
Valencia
Datum konání akce
13. 5. 2014
Typ akce podle státní příslušnosti
WRD - Celosvětová akce
Kód UT WoS článku
000339308100197