Critical Mass Task Identification in Projects
Identifikátory výsledku
Kód výsledku v IS VaVaI
<a href="https://www.isvavai.cz/riv?ss=detail&h=RIV%2F60460709%3A41110%2F19%3A81153" target="_blank" >RIV/60460709:41110/19:81153 - isvavai.cz</a>
Výsledek na webu
—
DOI - Digital Object Identifier
—
Alternativní jazyky
Jazyk výsledku
angličtina
Název v původním jazyce
Critical Mass Task Identification in Projects
Popis výsledku v původním jazyce
Critical Mass is a term that refers to some project activities which, even though not on the Critical Path, are very risky for in time project completion. Tasks potentially involved in critical mass are generally small, low priority, miscellaneous work, not linked to many others. A difference between activities on the Critical Path and those comprising a Critical Mass is that Critical Path activities must be completed as scheduled, in order to achieve the target completion date. Critical Mass activities generally have plenty of float or slack and can be executed just about any time and in any order. The aim of our paper is an identification of these activities based on quantitative indicators and to propose early warning system for project managers based on quantitative indicators, that such tasks exist and that they need to be financed and monitored. Our approach is an extension and modification of multi-criteria approach to activities criticalness and their expansion to the turnaround as
Název v anglickém jazyce
Critical Mass Task Identification in Projects
Popis výsledku anglicky
Critical Mass is a term that refers to some project activities which, even though not on the Critical Path, are very risky for in time project completion. Tasks potentially involved in critical mass are generally small, low priority, miscellaneous work, not linked to many others. A difference between activities on the Critical Path and those comprising a Critical Mass is that Critical Path activities must be completed as scheduled, in order to achieve the target completion date. Critical Mass activities generally have plenty of float or slack and can be executed just about any time and in any order. The aim of our paper is an identification of these activities based on quantitative indicators and to propose early warning system for project managers based on quantitative indicators, that such tasks exist and that they need to be financed and monitored. Our approach is an extension and modification of multi-criteria approach to activities criticalness and their expansion to the turnaround as
Klasifikace
Druh
D - Stať ve sborníku
CEP obor
—
OECD FORD obor
50204 - Business and management
Návaznosti výsledku
Projekt
—
Návaznosti
S - Specificky vyzkum na vysokych skolach
Ostatní
Rok uplatnění
2019
Kód důvěrnosti údajů
S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů
Údaje specifické pro druh výsledku
Název statě ve sborníku
Proceedings of the 37th International Conference on Mathematical Methods in Economics 2019
ISBN
978-80-7394-760-6
ISSN
—
e-ISSN
—
Počet stran výsledku
6
Strana od-do
344-349
Název nakladatele
Jihočeská univerzita v Českých Budějovicích
Místo vydání
České Budějovice
Místo konání akce
České Budějovice
Datum konání akce
11. 9. 2019
Typ akce podle státní příslušnosti
WRD - Celosvětová akce
Kód UT WoS článku
—