Základní podmínky pro modelování vysokonapěťových stanic
Identifikátory výsledku
Kód výsledku v IS VaVaI
<a href="https://www.isvavai.cz/riv?ss=detail&h=RIV%2F61989100%3A27240%2F08%3A00018980" target="_blank" >RIV/61989100:27240/08:00018980 - isvavai.cz</a>
Výsledek na webu
—
DOI - Digital Object Identifier
—
Alternativní jazyky
Jazyk výsledku
angličtina
Název v původním jazyce
The Basic Preconditions for Model of High Voltage Substation
Popis výsledku v původním jazyce
The real system from practice is selected for optimization purpose in this paper. We describe the real scheme of a high voltage (HV) substation 110/22 kV in different work states. The substations are important elements of the Moravian electric power network within transmission system of the Czech Republic. The part of the substation 110/22 kV ? substation 22 kV is being chosen for optimization purpose. The system is very complex -the substation 22 kV has two main busbars and one transfer busbar. There are sixteen outputs from the substation. Generally, the basic components of the HV substation are: a circuit breaker, a discloser, a voltage transformer, a circuit transformer, an overvoltage and current protection, a transformer of own consumption 22/0,4kV. The substation 22 kV has been chosen because it is very extensive power energy system in our region (Czech Republic) and we are able to obtain necessary data for the optimization analysis on the basis of intensive work contacts betwe
Název v anglickém jazyce
The Basic Preconditions for Model of High Voltage Substation
Popis výsledku anglicky
The real system from practice is selected for optimization purpose in this paper. We describe the real scheme of a high voltage (HV) substation 110/22 kV in different work states. The substations are important elements of the Moravian electric power network within transmission system of the Czech Republic. The part of the substation 110/22 kV ? substation 22 kV is being chosen for optimization purpose. The system is very complex -the substation 22 kV has two main busbars and one transfer busbar. There are sixteen outputs from the substation. Generally, the basic components of the HV substation are: a circuit breaker, a discloser, a voltage transformer, a circuit transformer, an overvoltage and current protection, a transformer of own consumption 22/0,4kV. The substation 22 kV has been chosen because it is very extensive power energy system in our region (Czech Republic) and we are able to obtain necessary data for the optimization analysis on the basis of intensive work contacts betwe
Klasifikace
Druh
D - Stať ve sborníku
CEP obor
JS - Řízení spolehlivosti a kvality, zkušebnictví
OECD FORD obor
—
Návaznosti výsledku
Projekt
—
Návaznosti
Z - Vyzkumny zamer (s odkazem do CEZ)
Ostatní
Rok uplatnění
2008
Kód důvěrnosti údajů
S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů
Údaje specifické pro druh výsledku
Název statě ve sborníku
ELEKTRO 08
ISBN
978-80-8070-845-0
ISSN
—
e-ISSN
—
Počet stran výsledku
4
Strana od-do
—
Název nakladatele
Žilinská univerzita
Místo vydání
Žilina
Místo konání akce
Žilina
Datum konání akce
20. 5. 2008
Typ akce podle státní příslušnosti
EUR - Evropská akce
Kód UT WoS článku
—