A Headrace Tunnel Reconstruction in Turkey
Identifikátory výsledku
Kód výsledku v IS VaVaI
<a href="https://www.isvavai.cz/riv?ss=detail&h=RIV%2F68407700%3A21110%2F19%3A00337478" target="_blank" >RIV/68407700:21110/19:00337478 - isvavai.cz</a>
Výsledek na webu
<a href="https://doi.org/10.14311/APP.2019.23.0025" target="_blank" >https://doi.org/10.14311/APP.2019.23.0025</a>
DOI - Digital Object Identifier
<a href="http://dx.doi.org/10.14311/APP.2019.23.0025" target="_blank" >10.14311/APP.2019.23.0025</a>
Alternativní jazyky
Jazyk výsledku
angličtina
Název v původním jazyce
A Headrace Tunnel Reconstruction in Turkey
Popis výsledku v původním jazyce
The operation of a hydro power project in North Turkey started in 2015. The project included the 12 km long headrace tunnel. An 8 km long lower (output) tunnel section was excavated by double shield (TBM technology) with 8.7 m ID. Due to problems with the mechanised excavation, a 4 km long upper (input) tunnel section was excavated as a counter drive done conventionally by the Drill and Blast (D&B) method with single shell lining generated from fibre reinforced sprayed concrete and rock bolts. Significant operational problems were observed in September 2016, about 16 months after its commissioning. The flooded tunnel was initially investigated by underwater Remotely Operated Vehicle (ROV) which indicated significant collapses in the tunnel. Operation of the power station had to be stopped and water from a supply dam at the headrace tunnel inlet had to be discharged to enable dewatering and inspection of the tunnel. Consequent investigation revealed three major collapses and a considerable variety of other damages in the D&B section of the tunnel, and significant damages were also observed in the tunnel section with segmental lining. Repair and strengthening of the tunnel was completed in October 2017, about one year after detection of these problems. A very fast tunnel re-opening was considered a significant success given the scale of damages and access difficulties. This paper is focused on all activities associated with the tunnel repair.
Název v anglickém jazyce
A Headrace Tunnel Reconstruction in Turkey
Popis výsledku anglicky
The operation of a hydro power project in North Turkey started in 2015. The project included the 12 km long headrace tunnel. An 8 km long lower (output) tunnel section was excavated by double shield (TBM technology) with 8.7 m ID. Due to problems with the mechanised excavation, a 4 km long upper (input) tunnel section was excavated as a counter drive done conventionally by the Drill and Blast (D&B) method with single shell lining generated from fibre reinforced sprayed concrete and rock bolts. Significant operational problems were observed in September 2016, about 16 months after its commissioning. The flooded tunnel was initially investigated by underwater Remotely Operated Vehicle (ROV) which indicated significant collapses in the tunnel. Operation of the power station had to be stopped and water from a supply dam at the headrace tunnel inlet had to be discharged to enable dewatering and inspection of the tunnel. Consequent investigation revealed three major collapses and a considerable variety of other damages in the D&B section of the tunnel, and significant damages were also observed in the tunnel section with segmental lining. Repair and strengthening of the tunnel was completed in October 2017, about one year after detection of these problems. A very fast tunnel re-opening was considered a significant success given the scale of damages and access difficulties. This paper is focused on all activities associated with the tunnel repair.
Klasifikace
Druh
J<sub>ost</sub> - Ostatní články v recenzovaných periodicích
CEP obor
—
OECD FORD obor
20101 - Civil engineering
Návaznosti výsledku
Projekt
<a href="/cs/project/TE01020168" target="_blank" >TE01020168: Centrum pro efektivní a udržitelnou dopravní infrastrukturu (CESTI)</a><br>
Návaznosti
P - Projekt vyzkumu a vyvoje financovany z verejnych zdroju (s odkazem do CEP)
Ostatní
Rok uplatnění
2019
Kód důvěrnosti údajů
S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů
Údaje specifické pro druh výsledku
Název periodika
Acta Polytechnica CTU Proceedings
ISSN
2336-5382
e-ISSN
2336-5382
Svazek periodika
23
Číslo periodika v rámci svazku
5
Stát vydavatele periodika
CZ - Česká republika
Počet stran výsledku
6
Strana od-do
25-30
Kód UT WoS článku
—
EID výsledku v databázi Scopus
—