Anchorage length of patented wire cables in prestressed bridge girders
Identifikátory výsledku
Kód výsledku v IS VaVaI
<a href="https://www.isvavai.cz/riv?ss=detail&h=RIV%2F00216305%3A26110%2F21%3APU142849" target="_blank" >RIV/00216305:26110/21:PU142849 - isvavai.cz</a>
Výsledek na webu
<a href="https://www.sciendo.com/article/10.2478/kom-2021-0012" target="_blank" >https://www.sciendo.com/article/10.2478/kom-2021-0012</a>
DOI - Digital Object Identifier
<a href="http://dx.doi.org/10.2478/kom-2021-0012" target="_blank" >10.2478/kom-2021-0012</a>
Alternativní jazyky
Jazyk výsledku
angličtina
Název v původním jazyce
Anchorage length of patented wire cables in prestressed bridge girders
Popis výsledku v původním jazyce
This paper briefly describes the methodology, performance and the obtained results of unique experiments performed on original I-73 precast bridge girders. The main objective of the experiments was to determine the actual anchorage length of corroded-through fully grouted prestressing reinforcement (prestressing wires), which is important for determination of the residual load-bearing capacity of prestressed structures. Observation probes leading all the way to the prestressing wires were drilled on selected sections of the girders along the length of the prestressing reinforcement. Optical image acquisition devices were then installed at these probes. Subsequently, controlled breakage of the patented wires (corrosion failure simulation) and observation of the changes that occurred in the prestressing wires after relief of stress were carried out. Evaluation of the experiments was then performed by analyzing the images obtained before and after the prestressing reinforcement failure.
Název v anglickém jazyce
Anchorage length of patented wire cables in prestressed bridge girders
Popis výsledku anglicky
This paper briefly describes the methodology, performance and the obtained results of unique experiments performed on original I-73 precast bridge girders. The main objective of the experiments was to determine the actual anchorage length of corroded-through fully grouted prestressing reinforcement (prestressing wires), which is important for determination of the residual load-bearing capacity of prestressed structures. Observation probes leading all the way to the prestressing wires were drilled on selected sections of the girders along the length of the prestressing reinforcement. Optical image acquisition devices were then installed at these probes. Subsequently, controlled breakage of the patented wires (corrosion failure simulation) and observation of the changes that occurred in the prestressing wires after relief of stress were carried out. Evaluation of the experiments was then performed by analyzing the images obtained before and after the prestressing reinforcement failure.
Klasifikace
Druh
J<sub>SC</sub> - Článek v periodiku v databázi SCOPUS
CEP obor
—
OECD FORD obor
20104 - Transport engineering
Návaznosti výsledku
Projekt
<a href="/cs/project/CK01000042" target="_blank" >CK01000042: Upřesnění zbytkové únosnosti předpjatých mostů</a><br>
Návaznosti
P - Projekt vyzkumu a vyvoje financovany z verejnych zdroju (s odkazem do CEP)
Ostatní
Rok uplatnění
2021
Kód důvěrnosti údajů
S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů
Údaje specifické pro druh výsledku
Název periodika
Koroze a ochrana materiálů
ISSN
0452-599X
e-ISSN
—
Svazek periodika
65
Číslo periodika v rámci svazku
3
Stát vydavatele periodika
CZ - Česká republika
Počet stran výsledku
96
Strana od-do
92-96
Kód UT WoS článku
—
EID výsledku v databázi Scopus