Modification of the BCWS by Work Effort
Identifikátory výsledku
Kód výsledku v IS VaVaI
<a href="https://www.isvavai.cz/riv?ss=detail&h=RIV%2F60460709%3A41110%2F15%3A68886" target="_blank" >RIV/60460709:41110/15:68886 - isvavai.cz</a>
Výsledek na webu
—
DOI - Digital Object Identifier
—
Alternativní jazyky
Jazyk výsledku
angličtina
Název v původním jazyce
Modification of the BCWS by Work Effort
Popis výsledku v původním jazyce
The paper deals with BCWS (Budgeted Cost for Work Performed) estimation by work effort in context of the Student Syndrome. Every existing activity in any project is, to a higher or lower extent, determined by the effect of the human agent, which commonlytakes a Student Syndrome form. If Student Syndrome phenomenon is completely expressed by means of a mathematical model, it would be possible to improve prediction of its impact on work effort in project activities. Successful duration of project activities is measured by the Earned value management (EVM) tools, where the BCWS is a key parameter. The BCWS is created by work effort in a project activity. Therefore, work effort has a hidden influence on EVM. Consequently, in the real world of human resources, the BCWS is not usually linear. This paper proposes new formulas for computing the BCWS in the project for Earned value management purposes. This proposal can be used for a more precise description of the real distribution of the wor
Název v anglickém jazyce
Modification of the BCWS by Work Effort
Popis výsledku anglicky
The paper deals with BCWS (Budgeted Cost for Work Performed) estimation by work effort in context of the Student Syndrome. Every existing activity in any project is, to a higher or lower extent, determined by the effect of the human agent, which commonlytakes a Student Syndrome form. If Student Syndrome phenomenon is completely expressed by means of a mathematical model, it would be possible to improve prediction of its impact on work effort in project activities. Successful duration of project activities is measured by the Earned value management (EVM) tools, where the BCWS is a key parameter. The BCWS is created by work effort in a project activity. Therefore, work effort has a hidden influence on EVM. Consequently, in the real world of human resources, the BCWS is not usually linear. This paper proposes new formulas for computing the BCWS in the project for Earned value management purposes. This proposal can be used for a more precise description of the real distribution of the wor
Klasifikace
Druh
D - Stať ve sborníku
CEP obor
BB - Aplikovaná statistika, operační výzkum
OECD FORD obor
—
Návaznosti výsledku
Projekt
—
Návaznosti
S - Specificky vyzkum na vysokych skolach
Ostatní
Rok uplatnění
2015
Kód důvěrnosti údajů
S - Úplné a pravdivé údaje o projektu nepodléhají ochraně podle zvláštních právních předpisů
Údaje specifické pro druh výsledku
Název statě ve sborníku
33rd International Conference Mathematical Methods in Economics MME 2015
ISBN
978-80-261-0539-8
ISSN
—
e-ISSN
—
Počet stran výsledku
6
Strana od-do
19-24
Název nakladatele
Faculty of Economics, University of West Bohemia, Plzen
Místo vydání
University of West Bohemia, Plzen
Místo konání akce
Cheb, Czech Republic
Datum konání akce
9. 9. 2015
Typ akce podle státní příslušnosti
WRD - Celosvětová akce
Kód UT WoS článku
—